QuanShun Webbing New Factory Update: Formwork Stripped, Masonry Advances on the Ground Floor
- Share
- publisher
- QuanShun Webbing Co., Ltd.
- Issue Time
- Nov 26,2026
Summary
Work at QuanShun Webbing Co., Ltd.'s new factory in Pinghu, Zhejiang, China, has reached the next milestone. As of November 13, 2026, the formwork panels supporting the ground-floor structure have been stripped and cleared, and masonry crews continue building interior brick walls. The project remains on schedule.

Following our last report on the ground floor, work at the new QuanShun Webbing Co., Ltd. factory in Pinghu has reached the next milestone. As of November 13, 2026, the formwork panels that shaped the ground-floor beams and slab have been stripped and cleared away, and masonry crews are pressing on with the interior brick walls. The frame stands complete up to the third floor, and the project remains on schedule.
Key Facts
- Date of update: November 13, 2026
- Previous milestone: ground-floor scaffolding dismantled and masonry begun (November 12, reported here)
- Completed since: ground-floor formwork panels stripped, dismantled and stacked for reuse
- Current stage: interior brick partition walls rising on the ground floor, with upper-level work continuing
- Status: on schedule
Ground-Floor Formwork Stripped and Cleared
The temporary formwork that shaped the ground-floor concrete is coming down. Working from scaffolding, crews are releasing the red formwork panels section by section from beneath the slab and beams, then lowering them to be cleaned and used again on the levels above. With the panels removed, the finished concrete soffits and beam edges are visible in the open for the first time. The photographs below were taken by the on-site project team on November 13, 2026.

Stripped panels and support steel are being gathered into orderly stacks rather than left scattered across the slab. Clearing the floor this way keeps the routes through the building open for masonry crews and material handling, and makes it easier to check the concrete surfaces while they are still accessible.

Brick Masonry Continues on the Ground Floor
While the formwork comes down overhead, the permanent walls are going up inside the frame. Masons are laying red perforated-brick partition walls against the concrete columns, following the layout marked out for rooms, corridors and service areas. Pallets of brick are staged close to each wall run so the laying crews can keep a steady pace without waiting on deliveries.

As each wall reaches its line and level, the ground floor is reading less like an open frame and more like a planned interior. The same sequence — strip and clear, then build the partitions — is being carried up through the building as each level becomes available.
Background and Implications
The new facility in Pinghu, Zhejiang, expands QuanShun Webbing's production capacity for outdoor furniture webbing, braided rope and woven rugs. With the ground-floor formwork stripped and interior walls advancing below, while structural work continues above, the project is moving on two fronts at once. That parallel progress keeps the path to installed weaving lines and shorter OEM and full-container lead times on track.
QuanShun Webbing will continue to publish dated photo updates as construction reaches each milestone. Site visits for sourcing partners can be arranged through the company's contact page once the interior areas are safe to access.
Update status: accurate as of November 13, 2026. The next scheduled milestones are continued brick masonry on the ground floor and formwork and structural work on the levels above.